On Monday and Tuesday we'll begin the process of shutting down the west alley between 4th & 5th street. Once the alley is shut down the storm sewer will be installed and the grading and removal of surface materials will follow the sewer install.
Community center parking lot will receive back fill in the tree & landscaping areas. Once the back fill is completed we can begin to open up the parking lot for parking. Late last week we poured concrete samples for both the "colored" and "stamped" ares. The samples are located near the flag pole at the fire station as well as in front of the old library entrance.
Early this morning the final water hook up should happen at the East end of the alley at Gambles and 1st class apparel. Thanks for the patience that everyone has extended us!