Monday, July 19, 2010

Continuing to work in the alleys:

We are hoping to get through the alleys so that we can begin pouring some concrete late this week or early next. I say this when it is pouring down rain so my guess is that we'll be off a day.

Monday: Staking of the West alley in preparation for final grade.
Tuesday - Thursday: Grading of the West alley in preparation of concrete.
Friday - Early next week: Pouring of the West alley. Once concrete is poured we'll need 3-4 days with no traffic on them before we open them up to the public.

On Monday the Downtown Committee is meeting to discuss stained and stamped concrete samples. The hope is that we can come to agreement on the samples so that we can give All American the go ahead on the gateway's into the downtown. {22&5th along with 1&B ave}.

No comments:

Post a Comment