Work will continue today at multiple locations.
A Place: The final pour on the West end nearest the ditch will be completed today. As well the approaches / drives have been poured to those residents and businesses along A Place.
4th Street: We should have back our initial compaction test today from Terracon and will evaluate the strength. As well the pouring of both sidewalks and driveway approach for FSB on the West side will be poured today.
B Avenue: With the delivery of more pipe it will allow the crew on B to get to the stop sign on the corner of 5th & B by the end of Tuesday or early on Wednesday.
Community Center Parking Lot: The curbing and sidewalk at the Fire station is being framed and should be poured on Tuesday / Wednesday of this week. We ran into one small issue on the West side of the community center that is delaying us in the final pouring of roughly a 10' x 10' section. We are working with Alliant to get a line shut off so that we can complete the final pour on the West side.
Alley's: The plan right now is to continue with the relocation of the hydrant nearest the Tuscan Moon and Bakery. As well as the relocation of the hydrant the line is being pressure tested so that we can start the installation of new service lines.
Downtown Revitalization Committee Meeting: Tonight at 5:30 the committee will be meeting to discuss funding and possible deductions for the project.