On Thursday morning All American will be cleaning up the dirt on B Avenue.
Community Center: Thursday we'll be pouring the sidewalk along the West side of the building as well as the sidewalk extending in front of the old library entrance. As well we are hoping to pour our colored / stamped samples for review and approval.
Downtown Revitalization Committee Meeting: On Tuesday evening the Downtown Revitalization Committee met to discuss the project. Some of the items that were discussed were the stamping of the 2' border along the sidewalks as well as the bump outs.
2' border: The plan is to have the border be both colored and stamped with the brick pattern for the entire downtown project.
Plaza (Bump-Outs): The plaza areas are now going to consist of a colored "hand tooled" pattern and not the 2'x2' slate stamping.
Alley's: Work is continuing in the alleys on the East end as they are working on getting the Library moved over to the new service.