Monday, November 8, 2010

Sidewalks & Bump Outs:

We had a very good week with getting 5th street sidewalks poured and opened up. This week we are going to work towards getting some of the bump outs completed and getting the North side of B Avenue ready for banding and sidewalks. As well on Sunday we had LL Pelling in town to stripe the majority of the downtown. We'll be completing the East side of B Avenue beginning at 10:00 Monday.

  • Bump outs on 5th Street will be completed.
  • Pouring of the intersection of 4th and B Avenue will be completed with the goal of having it opened up and ready for traffic on Friday
  • Installation of remainder of street lights on 5th Street.
  • Removal of sidewalks on the North side of B Avenue.
  • We are working on getting our first round of quilt blocks in early next week with the hopes of starting the installation process.
Thanks again for everyone's patience and if you have any questions please don't hesitate to ask.
Ryan