Thursday, October 21, 2010

Sidewalk Removal:

Well the removal of sidewalks has begun on 5th Street. The goal is to have gravel base replace the sidewalk immediately so that the surface can still be utilized by the public. We are looking to begin framing up of the 2' banding as early as Friday with the goal to have the pouring crew in on Monday to start.

The process will be that we'll pour the stamped banding and as soon as cured and cleaned come back in and pour the standard concrete up to the building. As with any old community we've run into some structural issues but have been working through those as they arise.

Again any questions please don't hesitate to ask.

Ryan