B Avenue & Fall Festival Update:

On Tuesday the concrete paving was finished on the East side of B Avenue. Our goal is that on Monday of next week the East side will meet the proper break strength so that we can finish up the two storm water inlets.

Our goal is to be able to have all of B Avenue opened up for traffic by the opening of the Fall Festival. As well we are going to look to fill in the areas between the streets and sidewalks with compacted back fill materials so that there will be a safe walkway from the street to the sidewalk.

Next week we'll also be focused on the cleaning up of the entry way's to the sidewalks as well as the alley approaches. All American and the City in cooperation with the Kalona Fire Dept. to make sure the streets and sidewalks are cleaned prior to the Fall Festival.

Thanks!